schedule the following activities using cpm
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)A — 1B A 4C A 3D B 2E C,D 5F D 2G F 2H E,G 3 a. Draw the network. b. What is the critical path? c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? The R&D department is planning to bid on a large project for the development of […]